Free Practice Test

Free PMP Practice Test (2026 Exam)

Check your readiness for the updated PMI Project Management Professional (PMP) exam with 50 situational questions across the People, Process and Business Environment domains, each with an instant explanation. Free to take, timed to the pace of the real exam, and retake it as often as you want.

25 or 50 Questions 65-Minute Timer 3 2026 Exam Domains Every Answer Explained New Sample Each Retake

New to PMP? Learn more about the certification →

Start Your Free Practice Test

Enter your details, then choose a 25-question Quick Test or the full 50-question, 65-minute practice test.

First Name
Last Name
Phone
About This Test

Free PMP Practice Test (2026 Exam)

This free PMP practice test from Training Camp, a PMI Authorized Training Partner, gives you 50 original scenario questions written to PMI's 2026 Examination Content Outline, the outline behind the updated exam that launched on July 9, 2026. Every answer choice has a written explanation, the questions are spread across the People, Process and Business Environment domains, and three of them share a short case scenario like the case-study section that opens the real exam. It is a readiness check, not a full study program, so if you want structured preparation, look at our PMP Boot Camp or read what the PMP certification is first.

What's on the PMI Project Management Professional (PMP) exam?

The 2026 PMP exam has 180 questions, 170 of which are scored and 10 of which are unscored pretest items, and you get 240 minutes. The exam opens with a case-study section, then moves to independent questions. Roughly 60 percent of the items reflect agile or hybrid approaches and about 40 percent are predictive.

Content is split across three domains: People (33%), Process (41%) and Business Environment (26%). PMI used AI and sustainability as inputs to the job task analysis behind the updated outline, so expect AI to appear as scenario context in planning, estimating and reporting items, alongside a stronger emphasis on value delivery and sustainability. PMI does not publish a numeric passing score; instead your report shows Above Target, Target, Below Target or Needs Improvement for each domain and overall.

How to use this practice test

Read each scenario the way PMI writes them: identify the situation, the approach in use (predictive, agile or hybrid) and what the project manager is being asked to do next. Then pick the answer that solves the root cause through the agreed process and through collaboration with the team and stakeholders. Read the explanation for every choice, including the ones you did not pick, because the reasoning behind a wrong answer is often what shows up as the right answer on a different question.

When you finish, use the domain breakdown to decide where to spend your study time. If Process is your weak spot, revisit approach selection, scope and schedule development, earned value, reserves and project closure; if People is low, focus on leading the team, stakeholder engagement, communication planning and knowledge transfer; if Business Environment is low, work on governance, change control, risk responses, managing issues and how a project responds when regulations or markets shift. The 65-minute timer gives you about the same time per question as the real exam, so treat the test as a pacing check as well as a knowledge check. Retake it as often as you like.

Domains Covered · 2026 Exam

People33%

Leading teams, conflict, stakeholders, communication planning and knowledge transfer.

Process41%

Approach selection, scope, schedule, cost, quality, procurement, value and closure.

Business Environment26%

Governance, compliance, change control, risk, issues, improvement and external change.

Try Before You Start

Sample PMP Practice Questions

Four questions from the bank, one per domain, with the reasoning behind every answer. The full test has 50.

Question 1 People

An agile team has been unable to run integration tests for two sprints because the shared test environment request is stuck in the procurement queue. At each daily standup the team raises the same blocker and looks to the project manager. As a servant leader, what should the project manager do next?

  1. Ask the team to build a temporary mock environment so integration testing can continue
  2. Remind the team that a self-organizing team is expected to resolve its own impediments
  3. Work directly with procurement to clear the request and report progress back to the team Correct
  4. Escalate the delay to the sponsor and request that the sprint goal be reduced
Why this is the best answer

Correct. Leading the team means representing the voice of the team and solving the problems it cannot solve itself, which is what servant leadership looks like in practice. Working the procurement blocker directly and reporting back is the project manager acting in service of the team.

Question 2 Process

A company is building a connected medical device. The hardware and its regulatory submission have fixed, well-understood requirements and a firm certification date, while the companion mobile app's user experience is expected to change based on clinician feedback. Which delivery approach should the project manager recommend?

  1. Predictive for the entire project, since regulatory work demands detailed up-front planning
  2. Agile for the entire project, since clinician feedback will drive the final product
  3. Predictive for the entire project, but freeze the app requirements after one round of clinician interviews so both components share a single baseline
  4. Hybrid, with a predictive approach for the hardware and regulatory work and an iterative approach for the app Correct
Why this is the best answer

Correct. Approach selection should follow the nature of the work. A hybrid life cycle applies predictive methods where requirements are stable and compliance-driven, and iterative methods where learning and change are expected.

Question 3 Business Environment

Case scenario: Harbor Point Logistics is replacing its warehouse management system at four distribution centers using a hybrid approach; the COO is the sponsor, Site 1 goes live in ten weeks and the system must integrate with a legacy ERP. The risk register lists the ERP vendor changing its interface, with a contingency plan to add an integration middleware layer if that happens. The vendor has just announced the interface will be retired six weeks from now. What should the project manager do next?

  1. Increase the risk's probability rating and monitor it closely
  2. Ask the COO to decide whether to delay the Site 1 go-live
  3. Log the event as an issue, execute the contingency plan, and update the risk register and schedule Correct
  4. Contact the vendor and request that the interface be kept available until after go-live
Why this is the best answer

Correct. When an identified risk's trigger fires and the event becomes certain, it is managed as an issue, and the 2026 outline expects the project manager to recognize that moment and manage it. The project manager records it in the issue log, executes the contingency plan, and updates the risk register and affected plans, escalating only if the response proves insufficient.

Every one of the 50 questions works this way: an explanation for the right answer and for the one you picked, so a wrong answer teaches you something. Questions last reviewed against the current PMI Project Management Professional (PMP) objectives.

PMP Practice Test

Frequently Asked Questions

Quick answers about the test, the PMI Project Management Professional (PMP) exam, and how to prepare.

Is this PMP practice test free?

Yes. Training Camp's PMP practice test is completely free. You get 50 scenario questions across the People, Process and Business Environment domains, with a written explanation for every answer choice.

How does this practice test work?

It is 50 multiple-choice questions written to PMI's 2026 Examination Content Outline, with an instant explanation after each answer and a 65-minute timer, which is timed to the pace of the real exam. Three questions share a short case scenario, similar to the case-study section on the real exam. You can retake it as often as you want.

How many questions are on the real PMP exam?

The updated PMP exam has 180 questions: 170 scored plus 10 unscored pretest items. You have 240 minutes, and the exam opens with a case-study section before moving to independent questions.

What score do I need to pass the PMP exam?

PMI does not publish a numeric passing score. Your result is reported as Above Target, Target, Below Target or Needs Improvement, both overall and by domain.

What domains does the PMP exam cover?

The 2026 exam covers three domains: People (33%), Process (41%) and Business Environment (26%). Roughly 60 percent of the questions reflect agile or hybrid approaches and about 40 percent are predictive.

What changed in the 2026 PMP exam?

The exam that launched on July 9, 2026 is built on PMI's updated Examination Content Outline. PMI used AI and sustainability as inputs to the job task analysis behind it, so expect AI to appear as scenario context in planning, estimating and reporting items; the exam also puts more emphasis on value delivery and sustainability, and opens with a case-study section.

What are the PMP eligibility requirements?

PMI's current requirements have four tiers of project leadership experience: 60 months with a high school diploma or equivalent secondary credential, 48 months with an associate or similar short-cycle degree, 36 months with a bachelor's degree, or 24 months with a degree from a GAC-accredited program. Every tier also requires 35 hours of project management training, which is waived if you hold an active CAPM. Qualifying experience must fall within the last 10 years.

How should you prepare for the PMP exam?

Study the PMI Examination Content Outline domain by domain, practice situational questions until the "what should the project manager do next" pattern feels natural, and consider a structured program such as Training Camp's PMP Boot Camp, which covers the 35 education hours and includes the exam voucher.